Dunkirk: over 4,050 tonnes of materials managed in 8 weeks!

12 November 2026

The teams from Energipole Remediation have just completed a soil decontamination project in Dunkirk, facing a dual challenge: the management of polluted land and land affected by Japanese knotweed, an invasive exotic plant species.

A technical site, carried out in a particularly constrained environment:
🔸 A pyrotechnic risk, necessitating the presence and oversight of a specialised company throughout the works.
🔸 The immediate proximity of residential areas, requiring a rigorous organisation of interventions.
🔸 Strict environmental requirements, particularly concerning the materials used and the preservation of wildlife and flora, in accordance with the prefectural decree.

For 8 weeks, our teams ensured selective excavation, sorting, characterisation, and the removal of materials to appropriate channels, before proceeding with backfilling and restoring the site.

✅ In total, over 4,050 tonnes of materials were managed!
👏 Congratulations to our teams for their dedication and diligence throughout this project.

Thank you to the Urban Community of Dunkirk (CUD), the project owner, and to DI Environment, the project manager, for their trust.